PJM-AG2-014
50 MW storage in White, IN · In queue since October 2020 · Proposed COD October 2023
50 MW
Capacity
1
Components
Battery
5y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
3 years
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
The proposed PJM-AG2-014 project is a 50 MW battery storage development in White County, Indiana. Interconnection is being managed through the PJM queue, with an entry date of October 19, 2020. The proposed commercial operation date is October 31, 2023.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Meadow Lake 345 kV substation. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Meadow Lake 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MEADOWLK34.5 KV MEDWLKWF
- POI Substation
- Meadow Lake Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.