PJM-AG2-020
7 MW storage in King George, VA · In queue since October 2020 · Proposed COD December 2022
7 MW
Capacity
1
Components
Battery
5y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
2y 2m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-30
The proposed energy storage project PJM-AG2-020 is a 7 MW battery development in King George County, Virginia. Interconnecting to the Dominion utility at the Arnolds Corner 34.5 kV point of interconnection, the project entered the PJM interconnection queue on October 23, 2020, with a proposed commercial operation date of December 30, 2022.
The project's interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
King George
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Arnolds Corner 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-020