PJM-AG2-037
4.7 MW generation in Allegheny, PA · In queue since November 2020 · Proposed COD December 2021
4.7 MW
Capacity
1
Components
Solar
5y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
1y 1m
Schedule
54 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-01
PJM-AG2-037 is a proposed solar generation project located in Allegheny County, Pennsylvania, within the PJM Interconnection region. The development project, with a total capacity of 4.7 MW, consists entirely of solar photovoltaic generation. Its point of interconnection is the Findlay-Clinton 23 kV line.
The project entered the PJM interconnection queue on November 13, 2020, with a proposed commercial operation date of December 1, 2021. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The designated utility for the project is DL (likely Duquesne Light).
Generated from interconnection queue and public data sources
State
PA
County
Allegheny
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DL
Entity
PJM
Service Type
—
Point of Interconnection
Findlay-Clinton 23 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-037