Van Dorn 34.5 kV
20 MW generation in Arlington, VA · In queue since February 2025
20 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Van Dorn 34.5 kV proposed project is a 20 MW generation project located in Arlington County, Virginia. The project is interconnected within the PJM Interconnection queue as project PJM-AG2-049, which was subsequently moved to queue TC2. The queue entry date is February 21, 2025.
The project's technology is listed as "Other." Dominion is the utility and the project's status is "active" in the interconnection queue. The service type is Generation Interconnection.
Generated from interconnection queue and public data sources
State
VA
County
Arlington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.