PJM-AG2-054
100 MW storage in Fulton, OH · In queue since December 2020 · Proposed COD September 2024
100 MW
Capacity
1
Components
Battery
5y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-25
PJM-AG2-054 is a proposed 100 MW battery storage project located in Fulton County, Ohio. The project, which consists of 100 MW of battery capacity, is interconnected to the ATSI utility via the Fulton 138 kV point of interconnection.
The project is listed in the PJM interconnection queue with an entry date of December 2, 2020, and a proposed commercial operation date of September 25, 2024. Its interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Fulton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Fulton 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- FULTONOP69 KV T1
- POI Substation
- Fulton Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-054