PJM-AG2-061
50 MW storage in Lasalle, IL · In queue since December 2020 · Proposed COD December 2023
50 MW
Capacity
1
Components
Battery
5y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
3 years
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AG2-061 is a proposed 50 MW battery storage project located in Lasalle County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on December 11, 2020. The proposed commercial operation date is December 31, 2023.
The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The project is located within the ComEd utility territory and connects to the Powerton-Nevada 345 kV point of interconnection. The developer is not specified in the available data.
Generated from interconnection queue and public data sources
State
IL
County
Lasalle
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Powerton-Nevada 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-061