Crooksville 69 kV
53 MW generation in Madison, KY · In queue since March 2025
53 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Crooksville 69 kV proposed project is a 53 MW solar generation facility located in Madison County, Kentucky. The project is being developed within the PJM Interconnection queue under queue ID PJM-AG2-073, which was moved to TC2. The queue entry date is March 4, 2025.
The project's interconnection status is active within the PJM queue. The interconnecting utility is EKPC. There is no proposed commercial operation date or interconnection agreement (IA) status available in the data. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
KY
County
Madison
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.