PJM-AG2-074
38 MW generation in Carbon, PA · In queue since January 2021 · Proposed COD December 2023
38 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 11m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
The proposed project PJM-AG2-074 is a 38 MW solar generation project located in Carbon County, Pennsylvania. Interconnecting to the PPL utility via the Meckesville Tap 69kV point of interconnection, the project entered the PJM interconnection queue on January 15, 2021. Its proposed commercial operation date is December 31, 2023.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
PA
County
Carbon
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Meckesville Tap 69kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- POI Substation
- Meckesville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-074