Project PJM-AG2-082 — Project Summary

Queue ID
PJM-AG2-082
Capacity
200 MW
Technology
Solar
Status
active
Location
Harrison, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AG2-082

PJM-AG2-082BetaActiveSolarPJMLBNL

200 MW generation in Harrison, OH · In queue since January 2021 · Proposed COD December 2024

200 MW

Capacity

1

Components

Solar

5y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection

Total Duration

3y 11m

Schedule

17 months past proposed COD

In Study38%
Queue EntryJan 22, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-01

About

PJM-AG2-082 is a proposed 200 MW solar generation project located in Harrison County, Ohio. The project is in the PJM interconnection queue, having entered on January 22, 2021, with a proposed commercial operation date of December 1, 2024. The interconnection agreement is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP.

The development project consists of 200 MW of solar photovoltaic generation. The point of interconnection is the Nottingham 138 kV substation.

Generated from interconnection queue and public data sources

Project Details

State

OH

County

Harrison

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Nottingham 138 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
02CPP_NH138 KV TR2
POI Substation
Nottingham Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.