Mt. Jackson DP-Mt. Jackson 115 kV
75 MW generation in Shenandoah, VA · In queue since February 2025
75 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Mt. Jackson DP-Mt. Jackson 115 kV project is a proposed 75 MW solar and battery storage hybrid generation project located in Shenandoah County, Virginia. The project is in the PJM interconnection queue as queue ID PJM-AG2-086, though it has been moved to TC2. The queue entry date is February 19, 2025. Dominion is the listed utility.
The project consists of both solar and storage components, though the individual capacities of each are not specified. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
VA
County
Shenandoah
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Mt. Jackson DP-Mt. Jackson 115 kV