Midlothian 230 kV
150 MW storage in Chesterfield, VA · In queue since February 2025
150 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Midlothian 230 kV project is a proposed 150 MW battery storage development in Chesterfield County, Virginia. The project is listed in the PJM interconnection queue as entry PJM-AG2-088, which was subsequently moved to queue TC2. Dominion is the utility associated with the project. The queue entry date is February 5, 2025.
The project is currently listed as active in the PJM queue, with a Generation Interconnection service type. There is recent news coverage of the project.
Generated from interconnection queue and public data sources
State
VA
County
Chesterfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Midlothian 230 kV