PJM-AG2-109
40 MW generation in Huron, OH · In queue since January 2021 · Proposed COD December 2023
40 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 11m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
The proposed project PJM-AG2-109 is a 40 MW solar generation project located in Huron County, Ohio. It is interconnected within the PJM Interconnection queue, having entered the queue on January 29, 2021. The proposed commercial operation date is December 31, 2023.
The interconnection agreement for the project with utility ATSI is currently in progress, with the specific study details unknown. The point of interconnection is the Fitchville-New London 69 kV line.
Generated from interconnection queue and public data sources
State
OH
County
Huron
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Fitchville-New London 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-109