Fitchville-New London 69 kV
40 MW generation in Huron, OH · In queue since February 2025
40 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Fitchville-New London 69 kV project is a proposed 40 MW solar generation project located in Huron County, Ohio. The project is being developed within the PJM Interconnection queue as project "PJM-AG2-109 - moved to TC2". The project's queue entry date is February 1, 2025.
The project is currently listed as active in the interconnection queue. The designated utility for interconnection is ATSI.
Generated from interconnection queue and public data sources
State
OH
County
Huron
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.