PJM-AG2-112
15.2 MW generation in Halifax, VA · In queue since January 2021 · Proposed COD March 2023
15.2 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 2m
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-24
PJM-AG2-112 is a proposed solar generation project with a total capacity of 15.2 MW. The project is located in Halifax County, Virginia, within the PJM Interconnection region. The queue entry date is January 29, 2021, with a proposed commercial operation date of March 24, 2023. Dominion is the utility associated with the project.
The interconnection status for PJM-AG2-112 is listed as "In Progress (unknown study)". The point of interconnection is the Perth 34.5 kV Substation (Circuit 404).
Generated from interconnection queue and public data sources
State
VA
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Perth 34.5 kV Substation (Circuit 404)
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-112