Dresden-Pontiac Midpoint 345 kV
100 MW generation in Livingston, IL · In queue since February 2025
100 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Dresden-Pontiac Midpoint 345 kV project is a proposed 100 MW solar generation project located in Livingston County, Illinois. The development project is in the PJM interconnection queue as project PJM-AG2-114, though it has been moved to the TC2 queue. The project's queue entry date is February 14, 2025.
The proposed project is located within the ComEd utility service area. The project is currently listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
IL
County
Livingston
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Dresden-Pontiac Midpoint 345 kV