PJM-AG2-116
100 MW hybrid in White, IN · In queue since January 2021 · Proposed COD October 2023
100 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
PJM-AG2-116 is a proposed 100 MW hybrid solar and battery project located in White County, Indiana. The project, which interconnects to the Olive-Reynolds 345 #1 345 kV substation, entered the PJM interconnection queue on January 29, 2021, with a proposed commercial operation date of October 31, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project consists of 100 MW of solar capacity coupled with battery storage. The interconnecting utility is AEP. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Olive-Reynolds 345 #1 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-116