PJM-AG2-124
33.34 MW generation in King And Queen, VA · In queue since January 2021 · Proposed COD December 2023
33.34 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 11m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AG2-124 is a proposed solar generation project located in King and Queen County, Virginia, within the PJM Interconnection region. The project, with a total capacity of 33.34 MW, is being developed within Dominion's service territory. It consists of 33.34 MW of solar photovoltaic generation.
The project entered the PJM interconnection queue on January 29, 2021, with a proposed commercial operation date of December 31, 2023. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Shackleford-Harmony 115 kV line.
Generated from interconnection queue and public data sources
State
VA
County
King And Queen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Shackleford-Harmony 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-124