PJM-AG2-125
15.44 MW generation in Preble, OH · In queue since January 2021 · Proposed COD December 2022
15.44 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 11m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
PJM-AG2-125 is a proposed solar generation project located in Preble County, Ohio, within the PJM Interconnection region. The project, with a total capacity of 15.44 MW, consists entirely of solar photovoltaic generation. Its point of interconnection is the Camden-Crystal 69 kV line.
The project entered the PJM interconnection queue on January 29, 2021, with a proposed commercial operation date of December 31, 2022. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The utility involved is Dayton.
Generated from interconnection queue and public data sources
State
OH
County
Preble
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Camden-Crystal 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM