PJM-AG2-126
150 MW hybrid in Vermillion, IN · In queue since January 2021 · Proposed COD June 2023
150 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 5m
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-30
PJM-AG2-126 is a proposed 150 MW hybrid solar and battery project located in Vermillion County, Indiana. The project, which consists of 150 MW of solar capacity, is in the PJM interconnection queue as of January 29, 2021, with a proposed commercial operation date of June 30, 2023. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Eugene 345 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
IN
County
Vermillion
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Eugene 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Eugene Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-126