PJM-AG2-130
55 MW generation in Van Buren, MI · In queue since February 2021 · Proposed COD December 2026
55 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AG2-130 is a proposed 55 MW solar generation project located in Van Buren County, Michigan. The project, which consists of 55 MW of solar photovoltaic generation, is in the PJM interconnection queue as of February 2, 2021, with a proposed commercial operation date of December 31, 2026. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Colby Tap-Valley 138 kV line.
Generated from interconnection queue and public data sources
State
MI
County
Van Buren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Colby Tap-Valley 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-130