PJM-AG2-143
20 MW generation in Clarion, PA · In queue since February 2021 · Proposed COD December 2026
20 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AG2-143 is a proposed solar generation project located in Clarion County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 20 MW, consists entirely of solar photovoltaic technology. The queue entry date for PJM-AG2-143 is February 16, 2021, with a proposed commercial operation date of December 31, 2026. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
The proposed point of interconnection (POI) for the project is the Burma-Sligo 25 kV line. The utility associated with the project is APS. The project is currently listed as active in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Clarion
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Burma-Sligo 25 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-143