PJM-AG2-148
130 MW hybrid in Wyandot, OH · In queue since February 2021 · Proposed COD December 2024
130 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 10m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-02
PJM-AG2-148 is a proposed 130 MW hybrid solar and battery project located in Wyandot County, Ohio. The project, consisting of 130 MW of solar capacity, is in the PJM interconnection queue as of February 22, 2021, with a proposed commercial operation date of December 2, 2024. The interconnecting utility is AEP, and the point of interconnection is the S Berwick - Galion 345 kV line.
The project's interconnection agreement status is listed as "In Progress (unknown study)". Recent news coverage of the project may exist.
Generated from interconnection queue and public data sources
State
OH
County
Wyandot
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
S Berwick - Galion 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-148