PJM-AG2-151
100 MW generation in Cumberland, VA · In queue since February 2021 · Proposed COD February 2024
100 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3 years
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-02
PJM-AG2-151 is a proposed solar generation project with a total capacity of 100 MW, located in Cumberland County, Virginia. The project is being developed within the Dominion service area and interconnected to the PJM grid at the Trices Lake - James River Tap 115 kV point of interconnection.
The project entered the PJM interconnection queue on February 23, 2021, with a proposed commercial operation date of February 2, 2024. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Trices Lake - James River Tap 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 955 RIVE16 KV RV-2
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.