PJM-AG2-159
61 MW hybrid in Grant, KY · In queue since February 2021 · Proposed COD September 2023
61 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 7m
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-09-15
PJM-AG2-159 is a proposed 61 MW hybrid solar and battery project located in Grant County, Kentucky. The project, which consists of 61 MW of solar generation, is in the PJM interconnection queue as of February 25, 2021, with a proposed commercial operation date of September 15, 2023. The interconnecting utility is EKPC, and the point of interconnection is the Williamstown 69 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)". Recent news coverage of the project may exist.
Generated from interconnection queue and public data sources
State
KY
County
Grant
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Williamstown 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WILLIAMS69 KV T4
- POI Substation
- Williamstown Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.