Project PJM-AG2-176 — Project Summary

Queue ID
PJM-AG2-176
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Crawford, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AG2-176

PJM-AG2-176BetaActiveSolarBatteryPJMLBNL

150 MW hybrid in Crawford, PA · In queue since February 2021 · Proposed COD January 2024

150 MW

Capacity

1

Components

Solar

5y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection

Total Duration

2y 11m

Schedule

27 months past proposed COD

In Study38%
Queue EntryFeb 26, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-01-31

About

PJM-AG2-176 is a proposed 150 MW hybrid solar and battery project located in Crawford County, Pennsylvania. The project consists of 150 MW of solar generation. It is listed in the PJM interconnection queue as of February 26, 2021, with a proposed commercial operation date of January 31, 2024. The point of interconnection is at the Geneva 115 kV substation.

The interconnection agreement status for the project is listed as "In Progress (unknown study)". The project is located within the PENELEC utility service area.

Generated from interconnection queue and public data sources

Project Details

State

PA

County

Crawford

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

PENELEC

Entity

PJM

Service Type

Point of Interconnection

Geneva 115 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
GENEVA 115 KV NO2 TX
POI Substation
Geneva Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.