PJM-AG2-179
60 MW hybrid in Adair, KY · In queue since February 2021 · Proposed COD September 2023
60 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 7m
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-09-15
PJM-AG2-179 is a proposed 60 MW hybrid solar and battery project located in Adair County, Kentucky. The project is interconnected within the PJM Interconnection queue as of February 26, 2021, with a proposed commercial operation date of September 15, 2023. The interconnecting utility is EKPC.
The project consists of 60 MW of solar generation capacity. Its interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
KY
County
Adair
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Coburg 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- COBURG 69 KV LD_181
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-179