PJM-AG2-184
210 MW generation in Knott, KY · In queue since February 2021 · Proposed COD June 2024
210 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 4m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
PJM-AG2-184 is a proposed solar generation project with a total capacity of 210 MW, located in Knott County, Kentucky. The project is in the PJM interconnection queue, having entered on February 27, 2021, with a proposed commercial operation date of June 1, 2024. The interconnecting utility is AEP.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Spicewood-Softshell 138 kV line.
Generated from interconnection queue and public data sources
State
KY
County
Knott
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Spicewood-Softshell 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-184