PJM-AG2-189
19.8 MW generation in Warren, NJ · In queue since February 2021 · Proposed COD February 2022
19.8 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1 year
Schedule
51 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-02-23
PJM-AG2-189 is a proposed solar generation project with a total capacity of 19.8 MW, located in Warren County, New Jersey. The project is interconnected to the JCPL utility network and is in the PJM interconnection queue, with an entry date of February 27, 2021. The proposed commercial operation date is February 23, 2022.
The interconnection agreement (IA) status for PJM-AG2-189 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Washington-Pequest River 34.5 kV line.
Generated from interconnection queue and public data sources
State
NJ
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Washington-Pequest River 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 955 RIVE16 KV RV-2
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-189