PJM-AG2-193
20 MW generation in Henrico, VA · In queue since February 2021 · Proposed COD December 2023
20 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 10m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AG2-193 is a proposed 20 MW solar generation project located in Henrico County, Virginia. The project is in the PJM interconnection queue as of February 27, 2021, with a proposed commercial operation date of December 31, 2023. Dominion is the utility associated with the project.
The interconnection agreement for PJM-AG2-193 is currently listed as "In Progress (unknown study)". The point of interconnection is the Turner 34.5 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Henrico
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Turner 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-193