PJM-AG2-198
80 MW generation in Prince Edward, VA · In queue since February 2021 · Proposed COD February 2024
80 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3 years
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-25
PJM-AG2-198 is a proposed 80 MW solar generation project located in Prince Edward County, Virginia. The project is in the PJM interconnection queue as of February 28, 2021, with a proposed commercial operation date of February 25, 2024. Dominion is the interconnecting utility.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Briery-Clover 230 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Prince Edward
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Briery-Clover 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-198