Briery - Finneywood 230 kV
80 MW generation in Prince Edward, VA · In queue since February 2025
80 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Briery - Finneywood 230 kV project is a proposed 80 MW solar generation project located in Prince Edward County, Virginia. The project is listed in the PJM interconnection queue as entry PJM-AG2-198, which was subsequently moved to queue TC2. The queue entry date is February 21, 2025.
The project is currently listed as active in the queue. Dominion is the utility and PJM is the entity associated with the project. Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
VA
County
Prince Edward
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.