PJM-AG2-200
20 MW generation in Warren, PA · In queue since March 2021 · Proposed COD January 2023
20 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 10m
Schedule
40 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-01-15
The proposed project PJM-AG2-200 is a 20 MW solar generation project located in Warren County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 2, 2021, with a proposed commercial operation date of January 15, 2023. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is located within the PENELEC utility service area. The point of interconnection is the North Warren_x0013_Russell 34.5 kV location.
Generated from interconnection queue and public data sources
State
PA
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
North Warren_x0013_Russell 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-200