PJM-AG2-202
20 MW storage in City Of Lynchburg, VA · In queue since March 2021 · Proposed COD October 2022
20 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 7m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-31
The proposed project PJM-AG2-202 is a 20 MW battery storage development located in the City of Lynchburg, Virginia. Interconnecting within the PJM Interconnection queue under American Electric Power (AEP), the project entered the queue on March 4, 2021, with a proposed commercial operation date of October 31, 2022.
The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Reusens 12.47 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
City Of Lynchburg
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Reusens 12.47 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- REUSENS 4 KV RE1
- POI Substation
- Reusens Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.