PJM-AG2-213
80 MW generation in Lunenburg, VA · In queue since March 2021 · Proposed COD December 2025
80 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 9m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
PJM-AG2-213 is a proposed solar generation project located in Lunenburg County, Virginia. The project, with a total capacity of 80 MW, is being developed within the Dominion service area. It consists of 80 MW of solar photovoltaic generation.
The project is currently active in the PJM interconnection queue, having entered the queue on March 8, 2021. Its proposed commercial operation date is December 1, 2025. The interconnection agreement (IA) status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Lunenburg
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Gary D.P Tap - Gary D.P 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-213