PJM-AG2-219
330 MW generation in Decatur, IN · In queue since March 2021 · Proposed COD December 2024
330 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-02
PJM-AG2-219 is a proposed solar generation project with a total capacity of 330 MW, located in Decatur County, Indiana. The project is in the PJM interconnection queue as of March 9, 2021, with a proposed commercial operation date of December 2, 2024. The interconnecting utility is AEP.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Jefferson-Greentown 765 kV line.
Generated from interconnection queue and public data sources
State
IN
County
Decatur
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Jefferson-Greentown 765 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-219