PJM-AG2-245
210 MW generation in Starke, IN · In queue since March 2021 · Proposed COD December 2023
210 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
PJM-AG2-245 is a proposed solar generation project with a total capacity of 210 MW, located in Starke County, Indiana. The project is in the PJM interconnection queue, having entered on March 16, 2021, with a proposed commercial operation date of December 1, 2023. The interconnecting utility is AEP.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Olive - Reynolds #1 345 kV line.
Generated from interconnection queue and public data sources
State
IN
County
Starke
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Olive - Reynolds #1 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-245