11 MW generation in Halifax, VA · In queue since March 2021 · Proposed COD December 2023
11 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
PJM-AG2-262 is a proposed solar generation project located in Halifax County, Virginia, within the Dominion service area. The project, with a total capacity of 11 MW, entered the PJM interconnection queue on March 18, 2021. The proposed commercial operation date is December 1, 2023.
The interconnection agreement for PJM-AG2-262 is currently listed as "In Progress (unknown study)". The point of interconnection is at the Dryburg 115 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Dryburg 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EDMONSON34.5 KV PINEYCSP