PJM-AG2-272
55 MW storage in Pittsylvania, VA · In queue since March 2021 · Proposed COD October 2024
55 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 7m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
PJM-AG2-272 is a proposed 55 MW battery storage project located in Pittsylvania County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 19, 2021. The developer is unknown. The proposed commercial operation date is October 1, 2024.
The interconnection agreement for PJM-AG2-272 is currently listed as "In Progress (unknown study)". The point of interconnection is the Berry Hill 138 kV substation. The project is within the service territory of utility AEP.
Generated from interconnection queue and public data sources
State
VA
County
Pittsylvania
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Berry Hill 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-272