Project PJM-AG2-281 — Project Summary

Queue ID
PJM-AG2-281
Capacity
50 MW
Technology
Battery
Status
active
Location
Queen Anne's, MD
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AG2-281

PJM-AG2-281BetaActiveBatteryPJMLBNL

50 MW storage in Queen Anne's, MD · In queue since March 2021 · Proposed COD May 2024

50 MW

Capacity

1

Components

Battery

5y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection

Total Duration

3y 2m

Schedule

24 months past proposed COD

In Study38%
Queue EntryMar 22, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-01

About

PJM-AG2-281 is a proposed 50 MW battery storage project located in Queen Anne's County, Maryland. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 22, 2021. The proposed commercial operation date is May 1, 2024. The project's interconnection agreement status is currently listed as "In Progress (unknown study)". The interconnecting utility is Delmarva Power & Light (DPL), and the point of interconnection is the Church 138 kV substation.

The development project consists solely of battery storage, with a total capacity of 50 MW. The project is currently listed as "active" within the PJM queue.

Generated from interconnection queue and public data sources

Project Details

State

MD

County

Queen Anne's

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

DPL

Entity

PJM

Service Type

Point of Interconnection

Church 138 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
CHURCH 69 KV CHURCHSP
POI Substation
Church Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AG2-281