PJM-AG2-281
50 MW storage in Queen Anne's, MD · In queue since March 2021 · Proposed COD May 2024
50 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
24 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-01
PJM-AG2-281 is a proposed 50 MW battery storage project located in Queen Anne's County, Maryland. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 22, 2021. The proposed commercial operation date is May 1, 2024. The project's interconnection agreement status is currently listed as "In Progress (unknown study)". The interconnecting utility is Delmarva Power & Light (DPL), and the point of interconnection is the Church 138 kV substation.
The development project consists solely of battery storage, with a total capacity of 50 MW. The project is currently listed as "active" within the PJM queue.
Generated from interconnection queue and public data sources
State
MD
County
Queen Anne's
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Church 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CHURCH 69 KV CHURCHSP
- POI Substation
- Church Substation