PJM-AG2-290
58 MW generation in Seneca, OH · In queue since March 2021 · Proposed COD December 2024
58 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-02
PJM-AG2-290 is a proposed solar generation project located in Seneca County, Ohio, with a total capacity of 58 MW. The project is interconnected to the PJM Interconnection queue, with an entry date of March 22, 2021, and a proposed commercial operation date of December 2, 2024. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is at the Amsden _x0013_ Fremont Center 69 kV line.
Generated from interconnection queue and public data sources
State
OH
County
Seneca
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Amsden _x0013_ Fremont Center 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-290