Cumberland 230 kV (PJM-AG2-297 - moved to TC2) — Project Summary

Queue ID
PJM-AG2-297 - moved to TC2
Capacity
19 MW
Technology
Solar
Status
active
Location
Cumberland, NJ
Region
PJM
Developer
IA Status

Cumberland 230 kV

PJM-AG2-297 - moved to TC2BetaActiveSolarPJMLive · PJM

19 MW generation in Cumberland, NJ · In queue since February 2025

19 MW

Capacity

0

Components

1y 3m

In Queue

IA Status

Interconnection

Total Duration

1y 3m

Pre-Study0%
Queue EntryFeb 28, 2025

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

The Cumberland 230 kV project is a proposed 19 MW solar generation project located in Cumberland County, New Jersey. The project is listed in the PJM interconnection queue as entry PJM-AG2-297, which was moved to queue TC2. The queue entry date is February 28, 2025.

The project's status is listed as active within the PJM queue. The interconnecting utility is AEC.

Generated from interconnection queue and public data sources

Project Details

State

NJ

County

Cumberland

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEC

Entity

PJM

Service Type

Generation Interconnection

Data Source

Live · PJM

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Cumberland 230 kV