Sulphur Creek-Loretto 69 kV
35 MW generation in Marion, KY · In queue since March 2025
35 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Sulphur Creek-Loretto 69 kV project is a proposed 35 MW solar generation project located in Marion County, Kentucky. The project is being developed within the PJM Interconnection queue under queue ID PJM-AG2-298, which was subsequently moved to queue TC2. The queue entry date is March 17, 2025.
The project is listed as active in the interconnection queue. The designated utility for the project is EKPC.
Generated from interconnection queue and public data sources
State
KY
County
Marion
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Sulphur Creek-Loretto 69 kV