PJM-AG2-300
100 MW storage in Frederick, VA · In queue since March 2021 · Proposed COD December 2023
100 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
The proposed project PJM-AG2-300 is a 100 MW battery storage development in Frederick County, Virginia. It is located within the PJM Interconnection region and is being managed by utility APS. The project entered the PJM queue on March 23, 2021, with a proposed commercial operation date of December 31, 2023.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is Meadow Brook 138 kV.
Generated from interconnection queue and public data sources
State
VA
County
Frederick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Meadow Brook 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MEADOWBR500 KV SVC
- POI Substation
- Meadow Brook Substation