PJM-AG2-310
100 MW storage in Roanoke, VA · In queue since March 2021 · Proposed COD December 2023
100 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AG2-310 is a proposed 100 MW battery storage project located in Roanoke County, Virginia. The project is interconnected within the PJM Interconnection queue, with an entry date of March 23, 2021. The proposed commercial operation date is December 31, 2023. The interconnection agreement status is listed as "In Progress (unknown study)".
The project, which is being developed within the AEP utility territory, consists of a single 100 MW battery component. The point of interconnection is the Matt Funk 138 kV substation. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
VA
County
Roanoke
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Matt Funk 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- KUMIS 138 KV T1
- POI Substation
- Matt Funk 138KV Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-310