PJM-AG2-327
10 MW generation in Bradford, PA · In queue since March 2021 · Proposed COD January 2023
10 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 10m
Schedule
40 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-01-15
PJM-AG2-327 is a proposed solar generation project located in Bradford County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 10 MW, consists entirely of solar photovoltaic technology. The proposed commercial operation date is January 15, 2023.
The project entered the PJM interconnection queue on March 24, 2021, and its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Tennessee Gas-East Towanda 115 kV substation. The utility is PENELEC.
Generated from interconnection queue and public data sources
State
PA
County
Bradford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Tennessee Gas-East Towanda 115 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-327