PJM-AG2-330
200 MW storage in Marshall, IN · In queue since March 2021 · Proposed COD December 2024
200 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-02
PJM-AG2-330 is a proposed 200 MW battery storage project located in Marshall County, Indiana. The project, which consists entirely of battery storage, is interconnected within the PJM Interconnection queue. Its queue entry date is March 25, 2021, with a proposed commercial operation date of December 2, 2024. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project is being developed within the American Electric Power (AEP) service territory and connects to the Dumont - Greentown 765 kV point of interconnection. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
IN
County
Marshall
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Dumont - Greentown 765 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DUMONT
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-330