PJM-AG2-343
100 MW storage in Fountain, IN · In queue since March 2021 · Proposed COD December 2024
100 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 9m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-02
PJM-AG2-343 is a proposed 100 MW battery storage project located in Fountain County, Indiana. The project is interconnected within the PJM Interconnection queue, with an initial queue entry date of March 26, 2021. The proposed commercial operation date is December 2, 2024.
The interconnection agreement status is currently listed as "In Progress (unknown study)". The designated point of interconnection (POI) is the Eugene - Dequine 345 kV line. The utility associated with the project is AEP.
Generated from interconnection queue and public data sources
State
IN
County
Fountain
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Eugene - Dequine 345 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-343