Eugene - Dequine 345 kV
150 MW storage in Fountain, IN · In queue since February 2025
150 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Eugene - Dequine 345 kV project is a proposed 150 MW battery storage project located in Fountain County, Indiana. The project is being developed within the PJM Interconnection queue as project "PJM-AG2-345 - moved to TC2", with a queue entry date of February 20, 2025.
The project is listed as active in the queue. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
IN
County
Fountain
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Eugene - Dequine 345 kV