PJM-AG2-347
448.8 MW generation in Sussex, DE · In queue since March 2021 · Proposed COD August 2025
448.8 MW
Capacity
1
Components
Offshore Wind
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 5m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-08-31
PJM-AG2-347 is a proposed offshore wind generation project with a total capacity of 448.8 MW. The project is located in Sussex County, Delaware, and is interconnected within the PJM Interconnection queue. The queue entry date is March 26, 2021, with a proposed commercial operation date of August 31, 2025. The Interconnection Agreement (IA) status is currently listed as "In Progress (unknown study)".
The proposed project is being developed within the Delmarva Power & Light (DPL) service territory. The point of interconnection (POI) is the Indian River 230 kV II substation. The project has appeared in recent news coverage regarding offshore wind development in the region.
Generated from interconnection queue and public data sources
State
DE
County
Sussex
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Indian River 230 kV II
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- INDIANRI13 KV UNIT10
- POI Substation
- Indian River South Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.