PJM-AG2-360
250 MW storage in Smyth, VA · In queue since March 2021 · Proposed COD November 2024
250 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 8m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-15
The proposed energy storage project PJM-AG2-360 is a 250 MW battery development in Smyth County, Virginia. The project is located within the PJM Interconnection region and is being managed by utility AEP.
The project entered the PJM queue on March 26, 2021, with a proposed commercial operation date of November 15, 2024. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Broadford 138 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Smyth
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Broadford 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BROADFORD
- POI Substation
- Broadford Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AG2-360